2021 Bond Updates

After months of finalizing behind the scene financials, perfecting project designs, and securing quality contractors, South Haven Public Schools is eager to move into the construction phase of the 2021 Bond Project, generously approved by voters last May. Soon construction trailers will set up shop and the visible work will begin. This initial stage of work focuses on Ratcliffe Field, our baseball/softball/tennis complex at the high school, and excavation at the Aylworth site. A lot of planning has gone into the project and it will be nice to move some dirt and see the improvement process firsthand. Thank you to the South Haven Community for your support and confidence!

LC MOHR HIGH SCHOOL

  • Site grading

  • Roof edge framing at dugouts

  • Fence detailing and site clean up

  • Brick install at high school building

  • Locker room benches

Previous Slide
Next Slide
Walkway at Baseball/Softball Field

AYLWORTH FIELDS

  • Redeveloped fields

  • Improve playing surfaces with drainage and irrigation

Aylworth Fields Site Plan

Previous Slide
Next Slide
Drinking Fountain

RATCLIFFE FIELD

  • Continued work on punch list items

WHAT'S NEXT

  • Roofing at the high school building

  • Continuing concrete curb at the varsity softball field

  • Fencing install at the baseball fields

  • Grading at the high school site

  • Bricking at high school building

  • Installing drinking fountain bollards at Ratcliffe Field

Groundbreaking Ceremony

Groundbreaking Ceremony - March 29, 2022
(Left to Right: Superintendent Schooley, BOE Trustee Grassflower, BOE Trustee Clevenger, BOE President Bos, Mr. Dee, Mr. Verseput, Mayor Smith)