High School Construction Timeline

 

Phase 1 - December 2015 to August 2016
Phased Construction photo

  • Setup construction staging areas
  • Demo Media Center and four Northeast classrooms
  • Remove corridor ceilings to provide access for new mechanical and electrical systems 
  • Construct new Science Labs
  • Construct new Learning Information Center 

Phase 2 - June 2016
 to August 2016

  • Renovate South and East Classrooms
  • Construct new Language Arts Classrooms
  • Renovate 3 Center Hall Classrooms
  • Install new electrical and mechanical systems
  • Install new technology infrastructure and equipment

Phase 3 - June 2016 to April 2017

  • Construct new Kitchen and Serving Area
  • Expand Cafeteria
  • New Student Success Center
  • New STEM Lab area that includes spaces for PLTW, Art, Industrial Arts, and Robotics

Phase 4 - April 2017 to August 2017

  • New Instrumental Music Room
  • Renovated Music Rooms
  • Renovated Main Offices
  • Renovations to Pool Area
  • Install new mechanical systems

Phase 5 - April 2017 to December 2017

  • Construct new and renovate Locker Rooms
  • Renovate Gym including new floor and bleachers